Pre-Treatment
Before painting the job, make sure that it is free from any dust, Rust For removing rust use de-rusting chemicals For removing oil or grease from the surface of the job use correct Oil removing chemicals.
Primer Coat
Before doing primer on job, make sure job has been cleaned & prepared by proper pre- treatment. Primer consist of Two Pack one is Base which is 4 Ltr packing & another called Hardener in 1 Ltr Packing. Mix the desired quantity of Base & hardener (Mixing Ratio is 3 : 1 Base to Hardener by volume). After mixing these two components in proper ratio stir well & allow this mixture to remain in stand still for 5 – 10 minutes. Use thinner EP-102 for adjusting viscosity of the mixture suitable for spraying. Allow primerd jobs to dry for at least for overnight.
Application of Putty
After the overnight apply Tuff-Seal Putty wherever necessary & after drying sand it properly touch up with primer on the putty applied area.
Finish Coat
On the next day of primer check hardness of the primer before applying finish coat. Paint consist of Two Pack one is Base which is 4 Ltr packing & another called Hardener in 1 Ltr Packing. Take two same types & of same volume containers for drawing the desired quantity of paint & hardener (Mixing Ratio is 3: 1 Base to Hardener by volume). After mixing these two components in proper ratio stir well & allow this mixture to remain in stand for 5 – 10 minutes. Use thinner EP-102 so as to adjust viscosity suitable for spraying.
Apply two coats of the same.